Hunter’s Walk Site

Gainesville, FL


  • Complete Site
  • Underground Retention System
  • Underground Retention System

This project was the complete site development of for a 5 acre retail development that included a Walgreens, a retail strip building, and a Campus USA Credit Union. It included demolition, water and sanitary sewer systems, electrical, phone infrastructure, underground utilities, retention, paving, sidewalks, landscaping, and irrigation.


Status Completed
Location Gainesville, FL
Size 5.17 acres
Duration 10 months
Completed August 2008
Architect AVID Group
Engineer AVID Group
Construction Type Site Work